The house at 813 Granite Estates Lane..... Click on any thumbnail for a huge view
08/12/2006Marked for Excavation
8/16/2006John Fortier Excavating
8/17/2006Big Hole
8/17/2006
8/18/2006Working on footingforms
8/18/2006Pouring main footings
8/18/2006
08/24/2006Finishing up placing the forms
8/24/2006Pouring the Walls
8/30/2006Forms Stripped, walls coated, starting to backfill
8/30/2006Basement plumbing & Radon Pipe roughed in
09/05/2006Basement floor poured
09/08/2006Window wells inSill plate on
09/08/2006Blacktop in
09/11/2006More Back fill
09/11/2006Working on floor support walls
9/13/2006Working on the floor
9/27/2006Floor Finished (& tarped for rain)Temp Electrical ready for hookup, working on forms for patio, driveway, porch & steps.
10/6/2006 Working on exterior framing
10/6/2006
10/13/2006
10/13/2006 Third bay of garage
10/13/2006 First interior walls done
10/24/2006 Trusses on
10/24/2006
10/27/2006 Roof on & covered
11/7/2006 Putting on Shingles
11/7/2006
12/08/2006 Corner of dining looking towards kitchen
12/08/2006 Corner of big garage looking in
12/08/2006 Looking towards front door from stairwell
12/08/2006 Stairwell
12/08/2006 South side
12/08/2006 East Side
12/08/2006 West (front)
12/08/2006
12/21/2006 Digging for Septic
12/21/2006 Trout Pond
12/29/2006 Starting Siding
12/29/2006
12/29/2006 Electrician Starting
12/29/2006 Heating unit set
01/06/2007 Siding
01/06/2007 Load of bricks
01/16/2007 Insulating
01/16/2007
01/16/2007 Rough-in electrical inspected
01/24/2007 Hanging drywall
01/24/2007
01/26/2007 Starting on porch posts
01/26/2007 House number
01/26/2007 Garage brick
02/16/2007 Painting
02/16/2007
02/21/2007 Working on cabinets
02/21/2007
03/08/2007 Loaded for the dump
03/09/2007 Driveway pour
03/09/2007 Lots of trim to be painted
03/09/2007 I'd buy this house just for the cabinets
03/09/2007
03/14/2007 Living area carpet
03/14/2007 Master Bedroom carpet
03/14/2007 Utility vinyl
04/03/2007 Backer board
04/03/2007
04/11/2007
04/17/2007
The Deck
The Back yard